PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 52 Topic 6 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 52 Topic 6 Discussion

PMI-ACP Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

An agile lead has been assigned to a project to develop an innovative digital device for a consumer products company. The company asked the agile lead to use a Scrum approach to product development. The product owner has worked on Scrum projects before and is excited about the value Scrum will bring to the company.

What should the scrum master do first?


A.

Build a product roadmapthat shows the features and releases.B Request an existing cross-functional team be dedicated to the project


B.

Obtain specific product requirements from a customer focus group.


C.

Develop a project budget based on the project charter.