Question #: 57
Topic #: 6

A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.

What should the scrum master do?


A.

Add the releases into a roadmap with milestones and activities.


B.

Identity dedicated tasks and activities with regular feedback loops.


C.

Deliver in small and continuous iterative releases.


D.

Identify the requirements' schedule within set time scales.