Question #: 51
Topic #: 6

While planning, what prioritization factors need to be considered for a minimally marketable feature (MMF)?


A.

How much risk is needed to develop an MMF


B.

How much money the organization will earn or save by having the MMF


C.

How many stakeholders are influencing the MMF


D.

How much time does an organization need to develop an MMF