PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 51 Topic 6 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-ACP Question # 51 Topic 6 Discussion

PMI-ACP Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

A team's technical lead believes that manual testing tasks should be conducted by junior team members below their level. The junior team members think it is unfair and refuse the tasks.

What should the Scrum Master do?


A.

Tell the technical lead to do the testing


B.

Facilitate an open and focused team discussion that reinforces team agreements


C.

Ask the team manager to advise the technical lead that all tasks are important


D.

Encourage the team to take ownership of the delivery


Get Premium PMI-ACP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.