Questions # 151:

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

Options:

A.

Compromising


B.

Collaborating


C.

Smoothing


D.

Problem Solving


Expert Solution
Questions # 152:

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

Options:

A.

Perform Quality Control


B.

Quality Metrics


C.

Perform Quality Assurance


D.

Plan Quality


Expert Solution
Questions # 153:

Which of the following is an example of the simplest fixed-price contract?

Options:

A.

Purchase requisition


B.

Purchase order


C.

Verbal agreement


D.

Request for quote


Expert Solution
Questions # 154:

The precedence diagramming method (PDM) is also known as:

Options:

A.

Arrow Diagram.


B.

Critical Path Methodology (CPM).


C.

Activity-On-Node (AON).


D.

schedule network diagram.


Expert Solution
Questions # 155:

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?

Options:

A.

There is a cost underrun.


B.

There is a cost overrun.


C.

The project may not meet the deadline.


D.

The project is 20 days behind schedule.


Expert Solution
Questions # 156:

Tools and techniques used for Plan Communications include the communication:

Options:

A.

requirements analysis, communication technology, communication models, and communication methods.


B.

methods, stakeholder register, communication technology, and communication models.


C.

requirements, communication technology, communication requirements analysis, and communication methods.


D.

management plan, communication technology, communication models, and communication requirements analysis.


Expert Solution
Questions # 157:

Which of the following events would result in a baseline update?

Options:

A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.


B.

A customer has approved a change request broadening the project scope and increasing the budget.


C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.


D.

One of the key project team resources has left the team and no replacement is available.


Expert Solution
Questions # 158:

One of the tools and techniques of the Manage Project Team process is:

Options:

A.

organization charts.


B.

ground rules.


C.

organizational theory,


D.

conflict management.


Expert Solution
Questions # 159:

Monte Carlo is which type of risk analysis technique?

Options:

A.

Probability


B.

Quantitative


C.

Qualitative


D.

Sensitivity


Expert Solution
Questions # 160:

A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?

Options:

A.

US$S000


B.

US$9500


C.

US$10,000


D.

US$12,500


Expert Solution
Questions # 161:

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

Options:

A.

Portfolio


B.

Process


C.

Project


D.

Program


Expert Solution
Questions # 162:

Which process involves identifying and documenting the logical relationships between project activities?

Options:

A.

Develop Schedule


B.

Sequence Activities


C.

Create WBS


D.

Applying leads and lags


Expert Solution
Questions # 163:

Project contracts generally fall into which of the following three broad categories?

Options:

A.

Fixed-price, cost reimbursable, time and materials


B.

Make-or-buy, margin analysis, fixed-price


C.

Time and materials, fixed-price, margin analysis


D.

Make-or-buy, lump-sum, cost-plus-incentive


Expert Solution
Questions # 164:

Which of the following is a tool or technique of the Define Activities process?

Options:

A.

Rolling wave planning


B.

Precedence diagramming method (PDM)


C.

Alternatives analysis


D.

Parametric estimating


Expert Solution
Questions # 165:

A required input for Create WBS is a project:

Options:

A.

quality plan.


B.

schedule network.


C.

management document update.


D.

scope statement.


Expert Solution