Questions # 136:

Which of the following types of a dependency determination is used to define the sequence of activities?

Options:

A.

Legal


B.

Discretionary


C.

Internal


D.

Resource


Expert Solution
Questions # 137:

How is the schedule variance calculated using the earned value technique?

Options:

A.

EV less AC


B.

AC less PV


C.

EV less PV


D.

AC less EV


Expert Solution
Questions # 138:

Lessons learned documentation is gathered during which of the following Project Management Process Groups?

Options:

A.

Planning


B.

Executing


C.

Closing


D.

Initiating


Expert Solution
Questions # 139:

A tool and technique used during the Perform Qualitative Risk Analysis process is:

Options:

A.

risk data quality assessment.


B.

variance and trend analysis.


C.

data gathering and representation techniques.


D.

risk audits.


Expert Solution
Questions # 140:

Which piece of information is part of the WBS Dictionary?

Options:

A.

Responsible organization


B.

Change requests


C.

Validated deliverables


D.

Organizational process assets


Expert Solution
Questions # 141:

Managing procurement relationships and monitoring contract performance are part of which process?

Options:

A.

Conduct Procurements


B.

Plan Procurements


C.

Administer Procurements


D.

Close Procurements


Expert Solution
Questions # 142:

Which of the following reduces the probability of potential consequences of project risk events?

Options:

A.

Preventive action


B.

Risk management


C.

Corrective action


D.

Defect repair


Expert Solution
Questions # 143:

Which tool or technique is used in Manage Stakeholder Expectations?

Options:

A.

Stakeholder management strategy


B.

Communication methods


C.

Issue log


D.

Change requests


Expert Solution
Questions # 144:

Which degree of authority does a project manager have on a project in a strong matrix organizational structure?

Options:

A.

Limited


B.

Low to moderate


C.

Moderate to high


D.

High to almost total


Expert Solution
Questions # 145:

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Options:

A.

WBS directory


B.

Activity list


C.

WBS


D.

Project schedule


Expert Solution
Questions # 146:

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

Options:

A.

Product scope description


B.

Procurement statement of work


C.

Project schedule


D.

Work breakdown structure (WBS)


Expert Solution
Questions # 147:

What does a CPI value greater than 1.0 indicate?

Options:

A.

Cost right at the estimated value


B.

Cost under the estimated value


C.

Cost right at the actual value


D.

Cost over the estimated value


Expert Solution
Questions # 148:

How many Project Management Process Groups are there?

Options:

A.

3


B.

4


C.

5


D.

6


Expert Solution
Questions # 149:

"Tailoring" is defined as the:

Options:

A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.


B.

act of creating a project team with the specialized skills required to produce a required product or service.


C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.


D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.


Expert Solution
Questions # 150:

Analogous cost estimating relies on which of the following techniques?

Options:

A.

Expert judgment


B.

Project management software


C.

Vendor bid analysis


D.

Reserve analysis


Expert Solution