What is project management?
Projects are separated into phases or subprojects; these phases include:
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
Which of the following is a strategy to deal with positive risks or opportunities?
The diagram below is an example of a:
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
Which risk response strategy is common for both positive and negative risks?
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
The cost benefit analysis tool is used for creating:
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
Which of the following is a tool and technique used to monitor risk?
The completion of the project scope is measured against the:
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS: