Questions # 76:

The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:

Options:

A.

Responses


B.

Appetite


C.

Tolerance


D.

Attitude


Expert Solution
Questions # 77:

Sensitivity analysis is typically displayed as a/an:

Options:

A.

Decision tree diagram.


B.

Tornado diagram.


C.

Pareto diagram.


D.

Ishikawa diagram.


Expert Solution
Questions # 78:

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:

Options:

A.

Project management plan.


B.

Project charter.


C.

Work breakdown structure.


D.

Stakeholder register.


Expert Solution
Questions # 79:

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

Options:

A.

A risk urgency assessment.


B.

The scope baseline.


C.

Work performance information.


D.

Procurement audits.


Expert Solution
Questions # 80:

An input to Conduct Procurements is:

Options:

A.

Independent estimates.


B.

Selected sellers.


C.

Seller proposals.


D.

Resource calendars.


Expert Solution
Questions # 81:

A project manager should document the escalation path for unresolved project risks in the:

Options:

A.

Change control plan


B.

Stakeholder register


C.

Risk log


D.

Communications management plan


Expert Solution
Questions # 82:

An output of the Direct and Manage Project Work process is:

Options:

A.

Deliverables.


B.

Activity lists.


C.

A work breakdown structure.


D.

A scope statement.


Expert Solution
Questions # 83:

Typical outcomes of a project include:

Options:

A.

Products, services, and improvements.


B.

Products, programs, and services.


C.

Improvements, portfolios, and services.


D.

Improvements, processes, and products.


Expert Solution
Questions # 84:

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50


B.

$100


C.

$125


D.

$175


Expert Solution
Questions # 85:

A temporary endeavor that creates a unique product or service is called a:

Options:

A.

Project


B.

Plan


C.

Program


D.

Portfolio


Expert Solution
Questions # 86:

A large portion of a projects budget is typically expended on the processes in which Process Group?

Options:

A.

Executing


B.

Planning


C.

Monitoring and Controlling


D.

Closing


Expert Solution
Questions # 87:

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

Options:

A.

Variance Analysis


B.

Define Scope


C.

Verify Scope


D.

Control Scope


Expert Solution
Questions # 88:

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:

Options:

A.

a control chart.


B.

baseline.


C.

Create WBS.


D.

decomposition.


Expert Solution
Questions # 89:

An input of the Create WBS process is:

Options:

A.

requirements documentation.


B.

scope baseline.


C.

project charter.


D.

validated deliverables.


Expert Solution
Questions # 90:

In the basic communication model, which term refers to the method that is used to convey the message?

Options:

A.

Decode


B.

Encode


C.

Medium


D.

Noise


Expert Solution