GAQM Associate in Project Management (APM) APM-001 Question # 84 Topic 9 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 84 Topic 9 Discussion

APM-001 Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?


A.

$50


B.

$100


C.

$125


D.

$175


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.