Questions # 1:

In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

Options:

A.

Technical approach


B.

Technical capability


C.

Business size and type


D.

Production capacity and interest


Expert Solution
Questions # 2:

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Options:

A.

Procurement documents


B.

Inspection and audits


C.

Estimate budget


D.

Risk register


Expert Solution
Questions # 3:

Specification of both the deliverables and the processes is the focus of:

Options:

A.

Change control


B.

Configuration control


C.

Project monitoring and control


D.

Issue control


Expert Solution
Questions # 4:

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

Options:

A.

Validate Scope.


B.

Plan Scope Management.


C.

Control Scope.


D.

Define Scope.


Expert Solution
Questions # 5:

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

Options:

A.

Critical path method


B.

Critical chain method


C.

Resource leveling


D.

Schedule network analysis


Expert Solution
Questions # 6:

Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

Options:

A.

Decomposition


B.

Inspection


C.

Project analysis


D.

Document analysis


Expert Solution
Questions # 7:

Which is an enterprise environmental factor?

Options:

A.

Marketplace conditions


B.

Policies and procedures


C.

Project files from previous projects


D.

Lessons learned from previous projects


Expert Solution
Questions # 8:

High-level project risks are included in which document?

Options:

A.

Business case


B.

Risk breakdown structure


C.

Project charter


D.

Risk register


Expert Solution
Questions # 9:

In the Define Activities process, the schedule management plan is used to:

Options:

A.

Capture the lessons learned from other projects for comparison.


B.

Contain the standard activity list.


C.

Document and support the project change requests.


D.

Prescribe the level of detail needed to manage the work.


Expert Solution
Questions # 10:

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

Options:

A.

Verified deliverables.


B.

Validated deliverables.


C.

Acceptance criteria.


D.

Activity resource requirements.


Expert Solution
Questions # 11:

A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

Options:

A.

triangular distribution


B.

tornado diagram


C.

beta distribution


D.

fishbone diagram


Expert Solution
Questions # 12:

Through whom do project managers accomplish work?

Options:

A.

Consultants and stakeholders


B.

Stakeholders and functional managers


C.

Project team members and consultants


D.

Project team members and stakeholders


Expert Solution
Questions # 13:

The following chart contains information about the tasks in a project.

Question # 13

Based on the chart, what is the schedulevariance (SV) for Task 8?

Options:

A.

-2,000


B.

-1,000


C.

1,000


D.

2,000


Expert Solution
Questions # 14:

Which project risk listed in the table below is most likely to occur?

Question # 14

Options:

A.

1


B.

2


C.

3


D.

4


Expert Solution
Questions # 15:

Completion of the product scope is measured against the product:

Options:

A.

prototypes


B.

requirements


C.

analyses


D.

benchmarks


Expert Solution