Questions # 46:

Which process in Project Time Management includes reserve analysis as a tool or technique?

Options:

A.

Estimate Activity Resources


B.

Sequence Activities


C.

Estimate Activity Durations


D.

Develop Schedule


Expert Solution
Questions # 47:

An element of the project scope statement is:

Options:

A.

Acceptance criteria.


B.

A stakeholder list.


C.

A summary budget,


D.

High-level risks.


Expert Solution
Questions # 48:

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

Options:

A.

Project document updates


B.

Activity list


C.

Activity attributes


D.

Project calendars


Expert Solution
Questions # 49:

An input to the Manage Project Team process is:

Options:

A.

Work performance reports.


B.

Change requests.


C.

Activity resource requirements.


D.

Enterprise environmental factors.


Expert Solution
Questions # 50:

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

Options:

A.

Customers.


B.

Business partners.


C.

Sellers.


D.

Functional managers.


Expert Solution
Questions # 51:

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

Options:

A.

Project team


B.

Focus group


C.

Change control board


D.

Project stakeholders


Expert Solution
Questions # 52:

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

Options:

A.

Bottom-up


B.

Parametric


C.

Analogous


D.

Three-point


Expert Solution
Questions # 53:

A reward can only be effective if it is:

Options:

A.

Given immediately after the project is completed.


B.

Something that is tangible.


C.

Formally given during project performance appraisals.


D.

Satisfying a need valued by the individual.


Expert Solution
Questions # 54:

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Options:

A.

Project Communications Management


B.

Project Integration Management


C.

Project Risk Management


D.

Project Scope Management


Expert Solution
Questions # 55:

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

Options:

A.

Facilitation techniques


B.

Expert judgment


C.

Analytical techniques


D.

Variance analysis


Expert Solution
Questions # 56:

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

Options:

A.

Monitor and Control Project Work


B.

Perform Quality Assurance


C.

Close Project or Phase


D.

Control Scope


Expert Solution
Questions # 57:

An output of the Develop Project Team process is:

Options:

A.

Organizational process assets.


B.

Enterprise environmental factors updates.


C.

Project staff assignments.


D.

Organizational charts and position descriptions.


Expert Solution
Questions # 58:

An input used in developing the communications management plan is:

Options:

A.

Communication models.


B.

Enterprise environmental factors.


C.

Organizational communications,


D.

Organizational cultures and styles.


Expert Solution
Questions # 59:

Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

Options:

A.

Procurement documents


B.

Communications plan


C.

Project charter


D.

Stakeholder register


Expert Solution
Questions # 60:

Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?

Options:

A.

Power/influence grid


B.

Power/interest grid


C.

Influence/impact grid


D.

Salience model