GAQM Associate in Project Management (APM) APM-001 Question # 55 Topic 6 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 55 Topic 6 Discussion

APM-001 Exam Topic 6 Question 55 Discussion:
Question #: 55
Topic #: 6

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?


A.

Facilitation techniques


B.

Expert judgment


C.

Analytical techniques


D.

Variance analysis


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.