APM-001 Exam Topic 6 Question 55 Discussion:
Question #: 55
Topic #: 6

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?


A.

Facilitation techniques


B.

Expert judgment


C.

Analytical techniques


D.

Variance analysis