Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
After Define Activities and Sequence Activities, the next process is:
Risk responses reflect an organization's perceived balance between:
Which of the following are three inputs to the risk register?
The correct equation for schedule variance (SV) is earned value:
The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
Which of the following is a group decision-making technique?
Administer Procurements is part of which Process Group?
Which characteristics do effective project managers possess?
The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
Which statement is true about the project management body of knowledge?
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
Risk exists the moment that a project is: