GAQM Associate in Project Management (APM) APM-001 Question # 116 Topic 12 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 116 Topic 12 Discussion

APM-001 Exam Topic 12 Question 116 Discussion:
Question #: 116
Topic #: 12

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?


A.

Initiating


B.

Planning


C.

Executing


D.

Monitoring and Controlling


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.