APM-001 Exam Topic 11 Question 108 Discussion:
Question #: 108
Topic #: 11

After Define Activities and Sequence Activities, the next process is:


A.

Estimate Activity Resources.


B.

Estimate Activity Durations,


C.

Develop Schedule.


D.

Control Schedule.