GAQM Associate in Project Management (APM) APM-001 Question # 119 Topic 12 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 119 Topic 12 Discussion

APM-001 Exam Topic 12 Question 119 Discussion:
Question #: 119
Topic #: 12

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:


A.

event.


B.

response,


C.

perception.


D.

impact.


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.