Questions # 166:

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:

Options:

A.

Determine Budget.


B.

Baseline Budget.


C.

Control Costs.


D.

Estimate Costs.


Expert Solution
Questions # 167:

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

Options:

A.

Control Schedule.


B.

Quality Control.


C.

Perform Integrated Change Control.


D.

Develop Schedule.


Expert Solution
Questions # 168:

Which provides the basic framework for managing a project?

Options:

A.

Project life cycle


B.

Work breakdown structure (WBS)


C.

Enterprise environmental factors


D.

Project initiation


Expert Solution
Questions # 169:

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

Options:

A.

Cost-reimbursable


B.

Time and material


C.

Fixed price or lump-sum


D.

Cost-plus-fixed-fee


Expert Solution
Questions # 170:

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

Options:

A.

Organizational breakdown structure (OBS)


B.

Work performance information


C.

Work package


D.

Work breakdown structure (WBS)


Expert Solution
Questions # 171:

Which type of chart is a graphic representation of a process showing the relationships among process steps?

Options:

A.

Control


B.

Bar


C.

Flow


D.

Pareto


Expert Solution
Questions # 172:

Which of the following is the primary output of the Identify Risks process?

Options:

A.

Risk management plan


B.

Risk register


C.

Change requests


D.

Risk response plan


Expert Solution
Questions # 173:

Which is an example of Administer Procurements?

Options:

A.

Negotiating the contract


B.

Authorizing contractor work


C.

Developing the statement of work


D.

Establishing evaluation criteria


Expert Solution
Questions # 174:

An output of Control Schedule is:

Options:

A.

A project schedule network diagram


B.

A schedule management plan


C.

Schedule data


D.

Schedule forecasts


Expert Solution
Questions # 175:

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

Options:

A.

Histograms


B.

Scatter diagrams


C.

Flowcharts


D.

Checksheets


Expert Solution
Questions # 176:

When is a Salience Model used?

Options:

A.

In a work breakdown structure (WBS)


B.

During quality assurance


C.

In stakeholder analysis


D.

During quality control (QC)


Expert Solution
Questions # 177:

Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?

Options:

A.

Product


B.

Cost-benefit


C.

Stakeholder


D.

Research


Expert Solution
Questions # 178:

Which of the following statements correctly characterizes pull communication?

Options:

A.

It includes letters, memos, reports, emails, and faxes.


B.

It requires recipients to access communication content at their own discretion.


C.

It is the most efficient way to ensure a common understanding among all participants.


D.

It is primarily used when the volume of information to be transferred is minimal.


Expert Solution
Questions # 179:

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

Options:

A.

BAC


B.

EAC


C.

ETC


D.

WBS


Expert Solution
Questions # 180:

Which of the following is an input to Direct and Manage Project Execution?

Options:

A.

Requested changes


B.

Approved change requests


C.

Work performance information


D.

Implemented defect repair


Expert Solution