APM-001 Exam Topic 17 Question 169 Discussion:
Question #: 169
Topic #: 17

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?


A.

Cost-reimbursable


B.

Time and material


C.

Fixed price or lump-sum


D.

Cost-plus-fixed-fee