GAQM Associate in Project Management (APM) APM-001 Question # 179 Topic 18 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 179 Topic 18 Discussion

APM-001 Exam Topic 18 Question 179 Discussion:
Question #: 179
Topic #: 18

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?


A.

BAC


B.

EAC


C.

ETC


D.

WBS


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.