GAQM Associate in Project Management (APM) APM-001 Question # 51 Topic 6 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 51 Topic 6 Discussion

APM-001 Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?


A.

Project team


B.

Focus group


C.

Change control board


D.

Project stakeholders


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.