GAQM Associate in Project Management (APM) APM-001 Question # 49 Topic 5 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 49 Topic 5 Discussion

APM-001 Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

An input to the Manage Project Team process is:


A.

Work performance reports.


B.

Change requests.


C.

Activity resource requirements.


D.

Enterprise environmental factors.