GAQM Associate in Project Management (APM) APM-001 Question # 78 Topic 8 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 78 Topic 8 Discussion

APM-001 Exam Topic 8 Question 78 Discussion:
Question #: 78
Topic #: 8

The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:


A.

Project management plan.


B.

Project charter.


C.

Work breakdown structure.


D.

Stakeholder register.