APM-001 Exam Topic 9 Question 86 Discussion:
Question #: 86
Topic #: 9

A large portion of a projects budget is typically expended on the processes in which Process Group?


A.

Executing


B.

Planning


C.

Monitoring and Controlling


D.

Closing