GAQM Associate in Project Management (APM) APM-001 Question # 88 Topic 9 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 88 Topic 9 Discussion

APM-001 Exam Topic 9 Question 88 Discussion:
Question #: 88
Topic #: 9

The technique of subdividing project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level is called:


A.

a control chart.


B.

baseline.


C.

Create WBS.


D.

decomposition.