GAQM Associate in Project Management (APM) APM-001 Question # 105 Topic 11 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 105 Topic 11 Discussion

APM-001 Exam Topic 11 Question 105 Discussion:
Question #: 105
Topic #: 11

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:


A.

dictionary.


B.

chart.


C.

report.


D.

register.