GAQM Associate in Project Management (APM) APM-001 Question # 104 Topic 11 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 104 Topic 11 Discussion

APM-001 Exam Topic 11 Question 104 Discussion:
Question #: 104
Topic #: 11

The completion of the project scope is measured against the:


A.

requirements documentation.


B.

project scope statement.


C.

project management plan.


D.

work performance measurements.