GAQM Associate in Project Management (APM) APM-001 Question # 99 Topic 10 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 99 Topic 10 Discussion

APM-001 Exam Topic 10 Question 99 Discussion:
Question #: 99
Topic #: 10

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?


A.

Reserve analysis


B.

Three-point estimating


C.

Parametric estimating


D.

Analogous estimating