Question #: 149
Topic #: 15

"Tailoring" is defined as the:


A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.


B.

act of creating a project team with the specialized skills required to produce a required product or service.


C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.


D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.