GAQM Associate in Project Management (APM) APM-001 Question # 157 Topic 16 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 157 Topic 16 Discussion

APM-001 Exam Topic 16 Question 157 Discussion:
Question #: 157
Topic #: 16

Which of the following events would result in a baseline update?


A.

A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.


B.

A customer has approved a change request broadening the project scope and increasing the budget.


C.

One of the risks identified in the risk management plan occurs, resulting in a schedule delay.


D.

One of the key project team resources has left the team and no replacement is available.