Question #: 152
Topic #: 16

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?


A.

Perform Quality Control


B.

Quality Metrics


C.

Perform Quality Assurance


D.

Plan Quality