GAQM Associate in Project Management (APM) APM-001 Question # 163 Topic 17 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 163 Topic 17 Discussion

APM-001 Exam Topic 17 Question 163 Discussion:
Question #: 163
Topic #: 17

Project contracts generally fall into which of the following three broad categories?


A.

Fixed-price, cost reimbursable, time and materials


B.

Make-or-buy, margin analysis, fixed-price


C.

Time and materials, fixed-price, margin analysis


D.

Make-or-buy, lump-sum, cost-plus-incentive


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.