GAQM Associate in Project Management (APM) APM-001 Question # 155 Topic 16 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 155 Topic 16 Discussion

APM-001 Exam Topic 16 Question 155 Discussion:
Question #: 155
Topic #: 16

A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?


A.

There is a cost underrun.


B.

There is a cost overrun.


C.

The project may not meet the deadline.


D.

The project is 20 days behind schedule.