GAQM Associate in Project Management (APM) APM-001 Question # 154 Topic 16 Discussion

GAQM Associate in Project Management (APM) APM-001 Question # 154 Topic 16 Discussion

APM-001 Exam Topic 16 Question 154 Discussion:
Question #: 154
Topic #: 16

The precedence diagramming method (PDM) is also known as:


A.

Arrow Diagram.


B.

Critical Path Methodology (CPM).


C.

Activity-On-Node (AON).


D.

schedule network diagram.


Get Premium APM-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.