You are the program manager for your organization. Your current program, which has just started, has eight projects and many of the projects share resources such as equipment and people. Management has asked that you identify when the project resources will be utilized on each project within your program. They are worried some resources may be idle or overscheduled. What approach can you use to consider the availability of resources when the project managers begin sequencing their project activities?
Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?
You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?
Which of the following directs the improvement efforts to those areas that will have the biggest impact?
You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?
You are the program manager for your organization and are planning the roles and responsibilities in your program. You would like to create a RACI chart for the program work. What does RACI mean?
A program is completed and the expected benefits are realized.
Before executing the transition and closing of the program, what should the program manager do?
Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B’s program manager has just advised that program B has been closed.
What should program A’s program manager update and review first with the stakeholders?
During the program execution stage, the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours.
What should the program manager do?
Hans is the program manager for his organization. His current project has seven constituent projects that each will create deliverables for the organization. Who is responsible for the project deliverables in this scenario?