PgMP Exam Topic 6 Question 77 Discussion:
Question #: 77
Topic #: 6

You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?


A.

Operational transfer plan


B.

Program transition plan


C.

Benefits transfer plan


D.

Program closure plan