Questions # 11:

A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program's benefits.

What should the program manager do to address these key stakeholders' concerns?

Options:

A.

Meet with the stakeholders and update the stakeholder map.


B.

Create a progress report to share with stakeholders after the next status meeting.


C.

Capture stakeholder expectations, and revise the stakeholder engagement plan.


D.

Update the communications management plan after meeting with the program steering committee.


Expert Solution
Questions # 12:

What analysis type could you use in a program to compare the positive stakeholders and their position, power, and influence over your program to the same variable components of the negative stakeholders in your program?

Options:

A.

Sensitivity analysis


B.

Stakeholder analysis


C.

Monte Carlo simulation


D.

Force field analysis


Expert Solution
Questions # 13:

Part of program management is to understand how the communication model works in a program. The program manager must be able to effectively communicate with the program team and stakeholders. What component of the communication model is responsible for carrying the message?

Options:

A.

Medium


B.

Sender


C.

Decoder


D.

Encoder


Expert Solution
Questions # 14:

You are a program manager of a program. You are required to compile performance data of your program. These data will be sent to relevant stakeholders. You are reviewing the status reports of all projects including the costs, schedule, scope, risks, and other performance data.

In which of the following processes are you working on?

Options:

A.

Plan Communication


B.

Distribute Information


C.

Report Program Performance


D.

Monitor and Control Program Performance


Expert Solution
Questions # 15:

You are the program manager for your company and evaluating the sellers to determine the seller to buy from. In your analysis you've created a histogram to display the pros and cons for each seller. You've created five categories of interest and assigned values to each category for each vendor. Your five categories are:

    Cost

    Schedule

    Experience

    Certification

    Warranty

Each category has a different point value and the vendor that receives the maximum points in total will win the contract. What type of seller evaluation are you performing?

Options:

A.

Monte Carlo simulation


B.

Expert judgment


C.

Weighted scoring model


D.

Benchmarking


Expert Solution
Questions # 16:

You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only

work 20 hours per week on the program. What is this limit of resource hours in a time period known as?

Options:

A.

Resource leveling heuristic


B.

Resource requirements


C.

Program risk


D.

Resource utilization


Expert Solution
Questions # 17:

The program manager of a multinational program must reconcile data including subject matter experts’ labor hour estimates, and other direct resource hour estimates. In addition, the program manager must prepare the cash flow analysis.

Which of the following should be considered to get a baseline budget?

Options:

A.

Currency exchange rates


B.

Component cost estimates


C.

Baseline schedule


D.

Program payment schedules


Expert Solution
Questions # 18:

A program to implement a company's new system is nearing completion and the program manager attempts to close the program. However, despite training provided to the operational staff on the new system, there is concern that the defined expected benefits will not be fully realized.

To prevent this concern in the future, which of the following should occur?

Options:

A.

Collaboration with the operational staff to develop the benefits sustainment plan


B.

Communication of the new capabilities' benefits to the operational staff


C.

Development and execution of a benefits transition plan to prepare the operational areas


D.

Identification of the risk in the program risk register and development of a plan to address the risk


Expert Solution
Questions # 19:

Part of program management is to identify what motivates your program team members. If you subscribe to Maslow's Hierarchy of Needs, which need is at the top of the hierarchy?

Options:

A.

Physiological


B.

Safety


C.

Self actualization


D.

Esteem


Expert Solution
Questions # 20:

June is the program manager for her organization. Management has asked June to create a visual mapping of the program scope so that all of the key stakeholders can see all of the elements of the program scope. June needs to create what kind of document to show all of the program deliverables based on the program scope?

Options:

A.

Program network diagram


B.

Program benefits mapping chart


C.

Program budget


D.

Program work breakdown structure