Pass the PMI PMI Certification PgMP Questions and answers with CertsForce

Viewing page 5 out of 14 pages
Viewing questions 41-50 out of questions
Questions # 41:

You are the program manager for your organization and are working with your team to identify stakeholders in the program. Where should the identified stakeholders and their information be recorded?

Options:

A.

Stakeholder matrix


B.

Communications management plan


C.

Requirements traceability matrix


D.

Stakeholder registry


Expert Solution
Questions # 42:

Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?

Options:

A.

Fallback plan


B.

Risk response plan


C.

Mitigation management plan


D.

Mitigation plan


Expert Solution
Questions # 43:

You are the program manager for your organization and are coaching Bonnie, a project manager, who would like to be a program manager wants to know what a program is. Which one of the following statements best defines what a program is for Bonnie?

Options:

A.

A program is a collection of projects that work together to create one deliverable for the organization


B.

A program is a collection of projects managed to gain benefits for the organization; the organization could not realize the benefits of the project if they were managed independently.


C.

A program is a uniform set of goals that are too large to be managed as one independent project so the project is subdivided into multiple objectives led by multiple project managers and orchestrated by one program manager.


D.

A program is a large collection of projects lead by a single project manager.


Expert Solution
Questions # 44:

You are the program manager for a new software development program. One of the developers has been adding extra fields for information in the software that was not part of the original program scope. While the fields are a good idea, the customer did not ask for the information and some time has been wasted on this work that was not in the program scope. This is an example of which one of the following terms?

Options:

A.

Preventive action


B.

Corrective action


C.

Gold plating


D.

Program scope change


Expert Solution
Questions # 45:

What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?


Expert Solution
Questions # 46:

A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?

Options:

A.

.93


B.

.82


C.

$323,889 D. -$38,889


Expert Solution
Questions # 47:

A program manager is leading a program to transform an organization's sales and customer service operations by introducing a new customer relationship management (CRM) solution. As the program progresses, the sponsor and other stakeholders are satisfied with the pace of the program's performance.

A stakeholder from the sales department now requests a new feature to integrate the CRM platform with another application. The program manager advises that this is out of scope, as it will require analysis and development and be a project on its own. The program manager then requests additional funding via the formal change management process and the new scope is approved.

What should the program manager do next?

Options:

A.

Secure additional approvals from senior stakeholders.


B.

Assign a new project manager to own the delivery of the new project.


C.

Redefine the priorities of the existing program components to ensure optimal resource allocation and management of interdependencies.


D.

Discontinue one of the existing program components, and reallocate all of that component's resources to the newly approved project.


Expert Solution
Questions # 48:

You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?

Options:

A.

The local government


B.

The change control board


C.

The stakeholders


D.

The program board


Expert Solution
Questions # 49:

Complete the following phrase about quality management: Quality isinto a program, notinto a program.

Options:

A.

Built, inspected


B.

Planned, inspected


C.

Planned, controlled


D.

Executed, controlled


Expert Solution
Questions # 50:

An unforeseen geopolitical risk impacts a program to establish a company’s operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately, what appeared to be a significant risk resulted in a negligible risk.

What should the program manager recommend to stakeholders for future, similar situations?

Options:

A.

Accept the risk


B.

Seek an expert opinion


C.

Establish an on-call risk response team


D.

Review the risk severity matrix


Expert Solution
Viewing page 5 out of 14 pages
Viewing questions 41-50 out of questions