PMI Program Management Professional (PgMP) PgMP Question # 66 Topic 5 Discussion

PMI Program Management Professional (PgMP) PgMP Question # 66 Topic 5 Discussion

PgMP Exam Topic 5 Question 66 Discussion:
Question #: 66
Topic #: 5

You are the program manager for a new software development program. One of the developers has been adding extra fields for information in the software that was not part of the original program scope. While the fields are a good idea, the customer did not ask for the information and some time has been wasted on this work that was not in the program scope. This is an example of which one of the following terms?


A.

Preventive action


B.

Corrective action


C.

Gold plating


D.

Program scope change


Get Premium PgMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.