An unforeseen geopolitical risk impacts a program to establish a company’s operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately, what appeared to be a significant risk resulted in a negligible risk.

What should the program manager recommend to stakeholders for future, similar situations?


A.

Accept the risk


B.

Seek an expert opinion


C.

Establish an on-call risk response team


D.

Review the risk severity matrix