PMI Program Management Professional (PgMP) PgMP Question # 79 Topic 6 Discussion

PMI Program Management Professional (PgMP) PgMP Question # 79 Topic 6 Discussion

PgMP Exam Topic 6 Question 79 Discussion:
Question #: 79
Topic #: 6

A program is completed and the expected benefits are realized.

Before executing the transition and closing of the program, what should the program manager do?


A.

Create a final program report


B.

Archive documents and lessons learned


C.

Obtain approval from the program governance board to initiate program closure activities


D.

Perform administrative and program management information system (PMIS) closure activities


Get Premium PgMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.