A program is completed and the expected benefits are realized.
Before executing the transition and closing of the program, what should the program manager do?
Create a final program report
Archive documents and lessons learned
Obtain approval from the program governance board to initiate program closure activities
Perform administrative and program management information system (PMIS) closure activities
Submit