Which of the following shows the ratio between a task's budgeted and actual costs?
You are the program manager for your program and are creating a communications management plan. Management wants you to address the type of communications based on the number of communication channels you'll have within the program. Currently there are 345 stakeholders in your program but next week you'll have 387 stakeholders. How many more communication channels will you have next week in your program?
The program manager wants to increase the team’s commitment to the program objectives.
The program manager should do which of the following?
During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized, the program manager was asked to transition the program into operations.
At this stage, what is expected during the post-review session organized by the program manager?
You are the program manager for your organization. Your current program, which has just been initiated, needs to launch several projects in order to create all of the benefits of the program. What document do you need to create in order to initiate the projects within your program?
The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality, and schedule objectives have been met, but costs and resource utilization are higher than expected. The program can no longer deliver the planned return-on- investment within an acceptable level and the intended benefits have not yet been realized.
After further analysis of the performance indicators, the program manager should do which of the following?
A program manager building the world’s largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?
Which of the following documents describes the details for each component in the WBS?
A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million.
Since the shutdown was not anticipated, what should the program manager do first?
You are the program manager for the BHN Program. Your program has 122 stakeholders that you'll need to plan to communicate with. Considering the size of the program how many communication channels do you have in this program?