Questions # 131:

A program has been established and preparation is complete.

Component projects are planned as a part of which of the following?

Options:

A.

Program definition phase


B.

Program formulation


C.

Program planning


D.

Program delivery phase


Expert Solution
Questions # 132:

You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

Options:

A.

Monitor and Control Program Scope


B.

Monitor and Control Project Performance


C.

Monitor and Control Program Schedule


D.

Manage Program Issues


Expert Solution
Questions # 133:

You are the program manager for your organization and you're coaching Tom, an aspiring program manager, on program management. Tom is curious about controlling communications. Which one of the following is an output of the communications control process?

Options:

A.

Approved change requests


B.

Communications management plan


C.

Stakeholder analysis charts


D.

Performance reports


Expert Solution
Questions # 134:

A company is rolling out an innovative program that includes new processes intended to define how the company will manage future programs. While program execution is going well, the program sponsor is concerned that the knowledge acquired needs to be reused for future programs.

What should the program manager do to ensure that the knowledge acquired is captured efficiently?

Options:

A.

Record lessons learned in the program management plan


B.

Create training materials summarizing team experiences and lessons learned


C.

Direct the project managers to create event logs to document their experiences and lessons learned


D.

Organize review sessions after each program stage to document successes, issues, and lessons learned


Expert Solution
Questions # 135:

Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.

Options:

A.

Half float


B.

Full float


C.

Total float


D.

Free float


Expert Solution
Viewing page 14 out of 14 pages