PMI Program Management Professional (PgMP) PgMP Question # 133 Topic 12 Discussion

PMI Program Management Professional (PgMP) PgMP Question # 133 Topic 12 Discussion

PgMP Exam Topic 12 Question 133 Discussion:
Question #: 133
Topic #: 12

Which of the following shows the ratio between a task's budgeted and actual costs?


A.

To-Complete Performance Index (TCPI)


B.

Schedule Variance (SV)


C.

Schedule Performance Index (SPI)


D.

Cost Performance Index (CPI)


Get Premium PgMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.