PMI Program Management Professional (PgMP) PgMP Question # 139 Topic 12 Discussion
PgMP Exam Topic 12 Question 139 Discussion:
Question #: 139
Topic #: 12
A program manager building the world’s largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?
A.
Finalize the business case and market analysis with the core program team and present the findings to the chief executive officer for approval.
B.
Work with the core program team to conduct a market analysis and make the decision based on the best return on investment.
C.
Arrange a meeting with both sponsors and the steering committee to present the market analysis and work through the conflict.
D.
Engage the program stakeholders, present the market analysis and findings to facilitate the decision on the best option.
Chosen Answer: