PMI Program Management Professional (PgMP) PgMP Question # 136 Topic 12 Discussion

PMI Program Management Professional (PgMP) PgMP Question # 136 Topic 12 Discussion

PgMP Exam Topic 12 Question 136 Discussion:
Question #: 136
Topic #: 12

During the last steering committee meeting, a program manager presented the benefits register to the program governance board. Since the intended benefits of the program were realized, the program manager was asked to transition the program into operations.

At this stage, what is expected during the post-review session organized by the program manager?


A.

Earned value (EV) report


B.

Customer sign-off


C.

Benefits register updates


D.

Feedback and lessons learned


Get Premium PgMP Questions

Contribute your Thoughts:


Chosen Answer: