The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.
(FIDIC Red Book (edition 2017) stipulates that the measurement shall be made as per the actual quantities executed at Site. Which one of the following statements is correct?)
Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.
Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
(Which two of the following statements are correct regarding types of Claims under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
You are the Contract Manager of the Engineer for a contract using FIDIC Yellow Book (edition 2017). You are drafting a notice holding the Commencement Date. Which one of the following approaches has the most clear and unambiguous drafting?
Giving " Notice " .... [2017 edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
(You are the Contract Manager of the Employer ' s Representative for a project using FIDIC Silver Book (edition 1999). The Contract Agreement does not define the Commencement Date. The Contract has been legally effective for 4 weeks. You are writing a letter urging the Employer to issue a Notice of Commencement Date. Why is this important? (2 correct answers apply))
(In the FIDIC Yellow Book (edition 1999), the Contractor has to provide the Engineer with documents as stated in Sub-Clause 5.2. Who is responsible for ensuring there is sufficient time allocated for reviewing these documents in relation to the Schedule of the Works?)