Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the FIDIC Contract Manager CCM Questions and answers with CertsForce

Viewing page 1 out of 5 pages
Viewing questions 1-10 out of questions
Questions # 1:

The FIDIC Red Book (edition 1999) deals with Value Engineering Clause. It follows from this clause that the Contractor shall give notice to the Engineer with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 to agree or determine this Cost, which shall be included in the Contract Price.

Options:

A.

True


B.

False


Expert Solution
Questions # 2:

(FIDIC Red Book (edition 2017) stipulates that the measurement shall be made as per the actual quantities executed at Site. Which one of the following statements is correct?)

Options:

A.

The measurement shall be always made of the net actual quantity of each item of the Permanent Works.


B.

The measurement shall be made of actual quantity of each item of the Permanent Works with allowance of shrinkage of the used materials.


C.

Measurements of the actual quantity of an item of the Permanent Works that was not specified in the Bill of Quantities, the Contractor will choose the appropriate price.


D.

None of the above are correct.


Expert Solution
Questions # 3:

Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?

Options:

A.

True


B.

False


Expert Solution
Questions # 4:

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Employer has an obligation to give a detailed notice to the Contractor about intended changes that are material to its financial arrangements.

Options:

A.

True


B.

False


Expert Solution
Questions # 5:

Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor failed to renew the Tender Security.


B.

The Contractor abandons the Works and the Employer did not issue Notice of termination.


C.

The Employer had submitted a claim under Sub-Clause 20.2.


D.

The Engineer had issued instruction to replace part of the Works.


E.

The Contractor failed to extend the validity of the Performance Security.


Expert Solution
Questions # 6:

(Which two of the following statements are correct regarding types of Claims under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The limit in time referred to in Sub-Clause 20.2.1 (also known as time bar) applies to all types of Claims.


B.

If a Claim is submitted as per sub-paragraph (c) of Sub-Clause 20.1, this is dealt with by the Engineer or Employer’s Representative (in case of FIDIC Silver Book) as per Sub-Clause 3.7/3.5.


C.

If a Claim is submitted as per sub-paragraphs (a) or (b) of Sub-Clause 20.1, it is dealt with in accordance with Sub-Clause 20.2, which specifically covers claims for time and/or money. Part of the procedure under Sub-Clause 20.2 is for a payment and/or an extension of time-related claim to be agreed or determined by the Engineer/Employer’s Representative (in case of the FIDIC Silver Book) in accordance with Sub-Clause 3.7/3.5.


D.

The time bar only applies to Contractor’s Claims and not to Employer’s Claims.


Expert Solution
Questions # 7:

You are the Contract Manager of the Engineer for a contract using FIDIC Yellow Book (edition 2017). You are drafting a notice holding the Commencement Date. Which one of the following approaches has the most clear and unambiguous drafting?

Options:

A.

I hereby give notice, in accordance with Sub-Clause 8.1 of the Conditions of Contract, the Commencement Date shall be 17 April 2023.


B.

The Contractor is kindly notified that the project shall be started by 17 April 2023.


C.

The commencement date of this project under Sub-Clause 8.1 of the Conditions of Contract will be 10 days from 7 April 2023.


D.

I hereby give notice, in accordance with Sub-Clause 1.1.84 and 8.2 of the Conditions of Contract, that the Time for Completion shall commence from 17 April 2023.


Expert Solution
Questions # 8:

Giving " Notice " .... [2017 edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

... is not a compulsory obligation, but " highly recommended " .


B.

... is always compulsory together with a clear indication of the relevant Sub-Clause under which the Notice is being served.


C.

... is a special obligation for the Engineer only, in order to enable him/her to manage the implementation of the contract.


D.

... is intended for written communications, in full compliance with the formal requirements outlined in the dedicated Sub-Clause.


Expert Solution
Questions # 9:

(You are the Contract Manager of the Employer ' s Representative for a project using FIDIC Silver Book (edition 1999). The Contract Agreement does not define the Commencement Date. The Contract has been legally effective for 4 weeks. You are writing a letter urging the Employer to issue a Notice of Commencement Date. Why is this important? (2 correct answers apply))

Options:

A.

If no notified Commencement Date were more than 8 weeks since the Contract became legally effective, the Contractor will be entitled to financial compensation.


B.

The Employer’s failure to notify the Commencement Date within 6 weeks after the date on which the Contract comes into full force and effect would constitute a breach of the Contract.


C.

If no notified Commencement Date were more than 8 weeks since the Contract was legally effective, the Contractor will be entitled to extension of time.


D.

The Contractor shall be entitled to give notice of termination if the Contractor does not receive a Notice of Commencement Date within 12 weeks after both Parties signed the Contract Agreement.


Expert Solution
Questions # 10:

(In the FIDIC Yellow Book (edition 1999), the Contractor has to provide the Engineer with documents as stated in Sub-Clause 5.2. Who is responsible for ensuring there is sufficient time allocated for reviewing these documents in relation to the Schedule of the Works?)

Options:

A.

Contractor


B.

Engineer


C.

Employer


Expert Solution
Viewing page 1 out of 5 pages
Viewing questions 1-10 out of questions