FIDIC Certified Contract Manager CCM Question # 6 Topic 1 Discussion

FIDIC Certified Contract Manager CCM Question # 6 Topic 1 Discussion

CCM Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

In the FIDIC Silver Book (edition 1999), if the Employer has instructed the Contractor as per Sub-Clause 8.6 to provide a revised programme to stay within Time of Completion, the Employer can claim additional costs. This only applies if the revised programme is still too slow to complete the Works within the Time for Completion. Is this statement true or false?


A.

True


B.

False


Get Premium CCM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.