Option B is correct: Notices are compulsory when required and must reference the relevant Sub-Clause to be valid.
Option D is correct: Notices are formal written communications and must comply with the contract’s prescribed procedures.
Option A is incorrect; notices are often mandatory, not merely recommended.
Option C is incorrect; notices are obligations for all Contract Participants, not just the Engineer.
[References:, , FIDIC Red, Yellow, Silver Books 2017 Edition, Sub-Clause 1.3 – Communications, , FIDIC Contract Manager Study Guide, Module on Notices and Communication, ]