FIDIC Certified Contract Manager CCM Question # 4 Topic 1 Discussion

FIDIC Certified Contract Manager CCM Question # 4 Topic 1 Discussion

CCM Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.

Which two of the following statements areNOTapplicable reasons?

(Choose all correct answers — multiple possibilities)


A.

Delay the execution of the Works or a Section.


B.

Decrease the Contract Price.


C.

Adversely affect the work of the Contractor's Personnel.


D.

Increase the performance of the Works when completed.


Get Premium CCM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.