Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

FIDIC Certified Contract Manager CCM Question # 5 Topic 1 Discussion

FIDIC Certified Contract Manager CCM Question # 5 Topic 1 Discussion

CCM Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).


A.

The Contractor failed to renew the Tender Security.


B.

The Contractor abandons the Works and the Employer did not issue Notice of termination.


C.

The Employer had submitted a claim under Sub-Clause 20.2.


D.

The Engineer had issued instruction to replace part of the Works.


E.

The Contractor failed to extend the validity of the Performance Security.


Get Premium CCM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.