(FIDIC Red Book (edition 2017) stipulates that the measurement shall be made as per the actual quantities executed at Site. Which one of the following statements is correct?)


A.

The measurement shall be always made of the net actual quantity of each item of the Permanent Works.


B.

The measurement shall be made of actual quantity of each item of the Permanent Works with allowance of shrinkage of the used materials.


C.

Measurements of the actual quantity of an item of the Permanent Works that was not specified in the Bill of Quantities, the Contractor will choose the appropriate price.